Unit Building – Point Arkwright
Rooftop Waterproofing Damage – Cracking in slab & blistering of the previous coating. Problems it caused – Water ingress to units below. Work done – Removed existing coating by mechanical grinding back to a clean substrate, rectified all cracks identified and applied a new 4 coat waterproofing system. Timeframe – 2 weeks.